In Maharashtra State the following organizations are implementing various Rail Line projects over last several decades:

  • Central Railway
  • South Central Railway
  • South East Central Railway
  • Western Railway
  • Konkan Railway Corporation Limited (KRCL)
  • Mumbai Railway Vikas Corporation Limited (MRVC)
  • Rail Vikas Nigam Limited (RVNL)

Despite their best efforts, only a total of 180 Kms. New line and 456 Kms. doubling has been commissioned during last seven years from 2011-12 to 2017-18 in Maharashtra State.

As against this performance, there are large number of projects sanctioned and are yet to be commissioned. As on 01-04-2018, there are 688 Kms. of new lines and 2449 Kms. of doubling is clearly sanctioned. Besides there are 1149 Kms. of new line, 106 Kms of gauge conversion and 124 Kms. of doubling are sanctioned with partial project funding from outside. Future 380 Kms. of new line is included in capital investment program 2016-17.

In addition to these sanctioned projects, there are 34 surveys sanctioned, covering length of 4220 Kms. Even if 20 % of these surveys get converted into sanction of the projects, it will increase the arrears of incomplete projects by another 844 kms.

With the aim of reducing these arrears, MRIDC has to take a lead role in implementing the projects in Maharashtra.

Sr. No. Name of projects Length in Km. Anticipated cost (Rs.Crs.) Status of sanction Progress Status Jurisdiction
1 Kalyan – Kasara 3rd line 67 792 Sanctioned 18% Central Rly.
2 Bhusawal – Jalgaon 3rd line 24 199 Sanctioned 35% Central Rly.
3 Wardha-Sewagram-Nagpur 3rd line 76 540 Sanctioned 15% Central Rly.
4 Wardha – Ballaharshah 3rd line 132 1272 Sanctioned 5% Central Rly.
5 Itarsi – Nagpur 3rd line 280 2449 Sanctioned 1% Central Rly.
6 Manmad – Jalgaon 3rd line 160 1035 Sanctioned Estimate sanctioned on 30.05.17 Central Rly.
7 Wardha – Nagpur 4th line 76 637 Sanctioned Estimate sanctioned on 20.04.17 Central Rly.
8 Jalgaon-Bhusawal 4th line 24 261 Sanctioned 10% Central Rly.
9 Pune – Miraj – Londha doubling 467 4795 Sanctioned 0% Central Rly.
10 Daund – Manmad doubling 236 2081 Sanctioned DPR sanctioned on 04.10.17 Central Rly.
11 Rajnandgaon-Nagpur 3rd line 182 1950 Sanctioned - SEC
Rly.
12 Daund-Gulbarga 225 3000 Sanctioned RVNL SC
Rly.
13 Mudkhed-Parbhani 81 950 Sanctioned RVNL Central Rly.
TOTAL 2030 19961
Sr. No. Name of projects Length in Km. Sanctioned cost (As per Pink Book) (Rs.Crs.) Latest cost as per DPR (Rs.Crs.) Status of sanction Jurisdiction
1 Ahmednagar – Beed-Parli Vaijnath 261 1134 2271 Sanctioned Pink Book Item No. 2 (Cost sharing 50:50) C. Rly.
2 Wardha – Nanded via Yavatmal – Pushad 285 1202 3168 Sanctioned Pink Book Item No. 4 (Cost sharing 60:40) C. Rly.
3 Baramati – Falton - lonand 54 163 736 Sanctioned Pink Book Item No. 3 (Rly. project) C. Rly.
4 Wadsa – Desai-Ganj-Gadhchiroli 54 277 756 Sanctioned Pink Book Item No. 2 (Cost sharing 50:50) S.E.C.Rly
5 Dighi Port – Roha 34 724 724 Sanctioned Pink Book Item No. 6 C. Rly.
Sub Total : 688 3500 7655
Sr. No. Name of projects Length in Km. Sanction cost (As per Pink Book)(Rs.Crs.) Latest cost as per DPR (Rs.Crs.) Status of sanction Jurisdiction
1 Pune – Nasik 265 2425 5341 Sanctioned with # Pink Book Item No. 8 (Cost sharing 50:50) C. Rly.
2 Vaibhaiv Wadi – Kolhapur 107 2750 3438 Sanctioned with # Pink Book Item No. 9 (Cost sharing 50:50) C. Rly.
3 Nagpur - Nagbhir (Gauge Conversion) 106 426 708 Sanctioned with # Pink Book Item No. 13 (Cost sharing 50:50) S.E.C. Rly
4 Jeur - Ashti 78 1560 1560 Sanctioned with # Pink Book Item No. 10 (Cost sharing 50:50) C. Rly.
5 Faltan - Pandharpur 105 1149 1149 Sanctioned with # Pink Book Item No. 11 (Cost sharing 50:50) C.Rly.
6 Hathkanagali -Ichalkaranji 8 160 191 Sanctioned with # Pink Book Item No. 12 (Cost sharing 50:50) C.Rly.
7 Karad - Chiplun 112 1200 1200 Sanctioned with # Pink Book Item No. 5 (Cost sharing 50:50) C.Rly.
8 Igatpur-Manmad (3rd line) 124 1860 1860 Sanctioned with # Pink Book Item No. 27 C.Rly.
Sub Total : 905 11530 15447

# Expenditure on these projects will be made only after following due process / mandatory approvals and sanctions.

Sr. No. Name of projects Length in Km. Sanctioned cost (As per Pink Book) (Rs.Crs.) Latest cost as per DPR (Rs.Crs.) Status of sanction Jurisdiction
1 Latur – Nanded via Loha & Ahmedpur(New line) 155 3100 3100 Included in Capital Investment Programme 2016-17 S.C.Rly.
2 Jalna – Khamgaon (New line) 155 3000 3000 Included in Capital Investment Programme 2016-17 S.C.Rly.
3 Gadchandur-Adilabad (Maharashtra & Telangana) 70 448 1500 Included in Capital Investment Programme 2016-17 S.C.Rly.
Sub Total : 380 6548 7600
Sr. No. Name of projects Length in Km. Sanctioned cost (As per Pink Book) (Rs.Crs.) Latest cost as per DPR (Rs.Crs.) Status of sanction Jurisdiction
1 Wadsa – Desai-Ganj-Gadhchiroli (NL) 54 277 756 Sanctioned Pink Book Item No. 2 (Cost sharing 50:50) S.E.C.Rly
2 Pune – Nasik (NL) 265 2425 5341 Sanctioned with # Pink Book Item No. 8 (Cost sharing 50:50) C. Rly.
3 Vaibhaiv Wadi – Kolhapur (NL) 107 2750 3438 Sanctioned with # Pink Book Item No. 9 (Cost sharing 50:50) C. Rly.
4 Nagpur - Nagbhir (Gauge Conversion) 106 26 708 Sanctioned with # Pink Book Item No. 13 (Cost sharing 50:50) S.E.C.Rly
5 Jeur – Ashti (NL) 78 1560 1560 Sanctioned with # Pink Book Item No. 10 (Cost sharing 50:50) C. Rly.
6 Faltan – Pandharpur (NL) 105 1149 1149 Sanctioned with # Pink Book Item No. 11 (Cost sharing 50:50)
7 Karad – Chiplun (NL) 112 1200 1200 Sanctioned with # Pink Book Item No. 5 (Cost sharing 50:50) C.Rly.
8 Igatpur-Manmad (3rd line) 124 1860 1860 Sanctioned with # Pink Book Item No. 27 C.Rly.
9 Latur – Nanded via Loha & Ahmedpur (NL) 155 3100 3100 Included in Capital Investment Programme 2016-17 S.C.Rly.
10 Jalna – Khamgaon (NL) 155 3000 3000 Included in Capital Investment Programme 2016-17 S.C. Rly.
11 Gadchandur-Adilabad (Maharashtra & Telangana) (NL) 70 448 1500 Included in Capital Investment Programme 2016-17 S.C.Rly.
Sr. No Project details Line Length in Kms. Blue Book – 2018-19 ref. no.
1 Chanda fort- Nagbhir Doubling 107 29
2 Mancherial –Gadchiroli (Telangana – Maharashtra) New line 115 33
3 Bilaspur-Nagpur (Chhatisgarh in Mah.) 4th line 412 (182 in Mah.) 34
4 Waraseone-Khairlanji-Tiroda (M.P & Mah) New line 50 36
5 Ramtek-Parshivani New line 36 37
6 Parbhani - Manmad Doubling 291 11
7 Parbhani - Parli Doubling 67 18
8 Godhan – Biloli – Murkhed-Jalkot-Latur Road New line 130 24
9 Bidar - Nanded New line 157 27
10 Manwath Road – Parli Vaidyanath via Sonpeth New line 67 28
11 Bolaram – Mudkhed Doubling 235 38
12 Washim-Mahur-Adilabad N ew line 189 13
13 Pandharpur - Bijapur New line 125 3
14 Kasara-Igatpuri 4th line 16 13
15 Karjat-Lonavala 4th line 28 8
16 Bhusawal-Badnera-Wardha 3rd line 314 15
17 Kalyan-Karjat 3rd line 46 14
18 Aurangabad-Chalisgaon New line 95 7
19 Ghatnandur-Shrigonda Road / Daund via Kaij, Manjarsumbha, Patoda and Jankhed New line 230 6
20 Karad-Kadegaon-Lenare-Kharsundi-Attapadi-Diganchi-Mahud-Pandharpur New line 160 5
21 Latur Road-Kurduwadi via Latur, Osmanabad New line 186 11
22 Pune-Baramati via Saswad-Jejuri-Moregaon New line 50 10
23 Miraj-Kavathemayhankal-Jath-Bijapur New line 122 4
24 Rotegaon - Puntamba New line 27 -
25 Betul-Chandur Bazar-Amravati New line 75 17
26 Rahuri - Shani Shingnapur New line 25 19
27 Titwala - Murbad New line 22 18
28 Shrirampur-Newasa-Shevgaon-Georai-Parli New line 230 20
29 Narkhed - Washim New line 232 21
30 Gulbarga-Latur New line 148 23
31 Warud - Arvi New line 60
32 Rotegaon – Kopargaon New Line 22 28
33 Bhusawal-Khandwa 3rd & 4th line 123 29
34 Wardha-Ballharshah 4th line 135 32